Project overview

Progresíve replaced all exhaust fans at Williamson Hall — including three large plume fans — in compliance with UF construction standards. Fans were relocated to backup generator power, and a 30-day load study confirmed the generator had capacity for the added load. Site surveys traced panels and breakers to correct mislabeled existing systems.
In a separate project, two air handling units serving an auditorium and lab spaces were consolidated into one, connected to existing chilled water and steam piping and controlled through VAV boxes.
Highlights
- 30-day load study for generator capacity
- Three plume exhaust fans on standby power
- AHU consolidation with VAV control