Project overview

Progresíve provided electrical system analysis, field coordination, and BIM integration during construction of a new two-story educational facility, covering service entrance equipment, generators, transfer switches, switchboards, panelboards, and transformers.
Our comprehensive report included short-circuit analysis, time-current coordination, and arc flash hazard analysis on all equipment, feeders, and branch circuits, EasyPower motor-start evaluations, and NFPA 70E labeling. Weekly cross-discipline meetings with the contractor kept the installation constructible.
Highlights
- Complete short-circuit, TCC & arc flash study
- 0.5 MW generator sequencing
- Weekly contractor coordination
- Full-building BIM model
- Completed on schedule with no change orders
- Equipment ratings evaluated against updated fault currents
- Temporary power kept mission-critical functions running during construction