Progresíve evaluated candidate service points of interconnection for a 1 MW array, assessed the fault contribution of the added generation at each location, and confirmed existing equipment interrupting and withstand ratings remained adequate with the array online. The point of interconnection was selected on analysis rather than proximity.
Highlights
- Fault contribution analysis
- Equipment rating verification
- Analysis-driven interconnection